Kentucky Interconnection Projects
interXdata tracks 801 interconnection projects in Kentucky representing 124,200 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Henderson, N/a, Trimble.
801Total projects
162Active
217Operational
414Withdrawn
124,200 MWRequested capacity
22,985 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 402 | 42,542 MW |
| Gas | 166 | 38,998 MW |
| Other | 148 | 30,361 MW |
| Battery | 51 | 6,593 MW |
| Solar+Battery | 20 | 2,739 MW |
| Coal | 4 | 1,740 MW |
| Wind | 6 | 860 MW |
| Hydro | 4 | 367 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Henderson | 24 | 6,377 MW |
| N/a | 23 | 4,604 MW |
| Trimble | 23 | 4,528 MW |
| Mercer | 23 | 2,786 MW |
| Hardin | 23 | 1,667 MW |
| Marshall | 22 | 4,483 MW |
| Muhlenberg | 21 | 8,125 MW |
| McCracken | 20 | 3,596 MW |
| Jefferson | 20 | 4,969 MW |
| Boone | 19 | 2,984 MW |
| Clark | 18 | 3,001 MW |
| Metcalfe | 18 | 2,691 MW |
| Fleming | 16 | 1,386 MW |
| Barren | 16 | 1,195 MW |
| Madison | 16 | 1,938 MW |
| Mercer County | 15 | 4,136 MW |
| Lawrence | 14 | 2,406 MW |
| Perry | 13 | 1,655 MW |
| Estill | 12 | 7 MW |
| Lee | 12 | 6 MW |
| Casey | 12 | 217 MW |
| Marion | 12 | 603 MW |
| Mason | 11 | 3,700 MW |
| Pike | 10 | 375 MW |
| Harrison | 10 | 540 MW |
| Jefferson County | 10 | 3,251 MW |
| Logan | 10 | 2,365 MW |
| Russell | 10 | 674 MW |
| Muhlenberg County | 9 | 4,332 MW |
| Hancock | 9 | 971 MW |
| Webster | 9 | 1,965 MW |
| Bourbon | 9 | 150 MW |
| Mccracken | 8 | 3,574 MW |
| Martin | 8 | 770 MW |
| Fayette | 8 | 302 MW |
| Daviess | 7 | 616 MW |
| Montgomery | 7 | 189 MW |
| Green | 7 | 745 MW |
| Henderson County | 7 | 1,778 MW |
| Hopkins | 7 | 345 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Southeast Queue Project 628 — Gas in Todd, Kentucky | 628 | Gas | 1,600.0 MW | active | Todd, Kentucky |
| KY Queue Project TC25-028 — Gas in Todd, Kentucky | TC25-028 | Gas | 1,513.0 MW | active | Todd, Kentucky |
| Southeast Queue Project 152 — Other in Muhlenberg, Kentucky | 152 | Other | 1,500.0 MW | withdrawn | Muhlenberg, Kentucky |
| Southeast Queue Project 629 — Gas in Todd, Kentucky | 629 | Gas | 1,224.0 MW | withdrawn | Todd, Kentucky |
| Hanging Rock-Jefferson 765kV | N43 | Other | 1,200.0 MW | withdrawn | Lewis, Kentucky |
| Southeast Queue Project 243 — Gas in Muhlenberg, Kentucky | 243 | Gas | 1,184.0 MW | operational | Muhlenberg, Kentucky |
| Stuart 345kV | AB1-169 | Gas | 1,150.0 MW | withdrawn | Mason, Kentucky |
| Jefferson - Hanging Rock 765 kV | AH2-351 | Solar | 1,000.0 MW | withdrawn | N/a, Kentucky |
| Jefferson - Hanging Rock 765 kV | AH2-353 | Solar | 1,000.0 MW | withdrawn | N/a, Kentucky |
| MISO Queue Project G108 — Other in Henderson, Kentucky | G108 | Other | 1,000.0 MW | withdrawn | Henderson, Kentucky |
| Southeast Queue Project 137 — Other in Mccracken, Kentucky | 137 | Other | 950.0 MW | withdrawn | Mccracken, Kentucky |
| MISO Queue Project G070 — Other in Mccracken, Kentucky | G070 | Other | 900.0 MW | withdrawn | Mccracken, Kentucky |
| Trimble County | 6071_2 | Other | 834.0 MW | operational | Trimble, Kentucky |
| KY Queue Project LGE-GIS-2013-002 — Gas in Muhlenberg County, Kentucky | LGE-GIS-2013-002 | Gas | 807.0 MW | withdrawn | Muhlenberg County, Kentucky |
| Southeast Queue Project 106 — Other in Logan, Kentucky | 106 | Other | 800.0 MW | withdrawn | Logan, Kentucky |
| KY Queue Project LGE-GIS-2011-004 — Gas in Mercer County, Kentucky | LGE-GIS-2011-004 | Gas | 790.0 MW | withdrawn | Mercer County, Kentucky |
| Laurel-Cooper 161 kV | AH1-721 - moved to TC2 | Gas | 786.0 MW | active | N/a, Kentucky |
| PJM Queue Project AH1-721 — Gas in an unlisted county, Kentucky | AH1-721 | Gas | 786.0 MW | active | Kentucky |
| East Bend | 6018_2 | Other | 772.0 MW | operational | Boone, Kentucky |
| Baker 345kV | W1-035 | Gas | 750.0 MW | withdrawn | Lawrence, Kentucky |
| MISO Queue Project G019 — Gas in Oldham, Kentucky | G019 | Gas | 750.0 MW | operational | Oldham, Kentucky |
| MISO Queue Project G218 — Coal in Trimble, Kentucky | G218 | Coal | 750.0 MW | operational | Trimble, Kentucky |
| KY Queue Project RSC26-003 — Gas in McCracken, Kentucky | RSC26-003 | Gas | 750.0 MW | active | McCracken, Kentucky |
| KY Queue Project LGE-GIS-2007-001 — Gas in Muhlenberg County, Kentucky | LGE-GIS-2007-001 | Gas | 750.0 MW | withdrawn | Muhlenberg County, Kentucky |
| Southeast Queue Project 145 — Other in Muhlenberg, Kentucky | 145 | Other | 750.0 MW | withdrawn | Muhlenberg, Kentucky |
| Southeast Queue Project 146 — Other in Muhlenberg, Kentucky | 146 | Other | 750.0 MW | withdrawn | Muhlenberg, Kentucky |
| Mill Creek (KY) | 1364_5 | Gas | 740.0 MW | active | Jefferson, Kentucky |
| KY Queue Project 417 — Gas in Muhlenberg, Kentucky | 417 | Gas | 720.0 MW | active | Muhlenberg, Kentucky |
| Reid EHV | J3089 | Gas | 696.0 MW | withdrawn | Webster, Kentucky |
| Southeast Queue Project 174 — Other in Monroe, Kentucky | 174 | Other | 683.0 MW | withdrawn | Monroe, Kentucky |
Top developers in Kentucky
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Geenex Solar, LLC | 3 | 440 MW |
| ACE Development Company, LLC | 3 | 230 MW |
| Sunflower Prairie Solar Project, LLC | 2 | 79 MW |
| SR Fayette II, LLC | 2 | 70 MW |
| Round Trip, LLC | 2 | 121 MW |
| Exie Solar, LLC | 2 | 300 MW |
| STMO bn, LLC | 2 | 410 MW |
| East Kentucky Power Cooperative, Inc. | 2 | 1,002 MW |
| Wood Duck Solar LLC | 2 | 100 MW |
| Goldfinch Solar, LLC | 2 | 500 MW |
| Hummingbird Energy LLC | 2 | 180 MW |
| Wildrye Solar LLC | 2 | 104 MW |
| Coneflower Solar 2 LLC | 2 | 250 MW |
| South Fork Solar, LLC | 2 | 45 MW |
| Scotland Solar, LLC | 1 | 100 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-24 | KY Queue Project RSC26-003 — Gas in McCracken, Kentucky | new_project | — | active |
| 2026-08-24 | KY Queue Project SP-001 — Battery in Marshall, Kentucky | phase | Deficiency Check | Facilities Study |
| 2026-08-24 | KY Queue Project 609 — Solar in McCracken, Kentucky | poi_name | Shawnee 161kV Buss | Shawnee 161-kV Substation |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; lgeku-oasis; MISO — generator interconnection queue; PJM — new-services interconnection queue; tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in Kentucky.