Brazos Bend Storage SLF (29INR0164)

Brazos Bend Storage SLF is a 243.0 MW battery interconnection project in Milam, Texas with a current status of withdrawn.

243.0 MWCapacity
WithdrawnStatus
MilamMarket
BatteryTechnology

Project facts

Canonical nameBrazos Bend Storage SLF
Queue ID29INR0164
Statuswithdrawn
Source status—
MarketMilam
TechnologyBattery
Capacity243.0 MW
StateTexas
CountyMilam
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date—
Withdrawn date2026-08-19
Developer—
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30developerGrenergy USA—low
2026-09-30poi_name345 kV Line (3765) GRISTMILL_5 to (39950) TNTNP_ONE_3—low
2026-09-30phaseSS Completed, FIS Started, No IA—low
2026-09-30operational_date2029-09-17—medium
2026-09-30withdrawn_date—2026-08-19high
2026-09-30statusoperationalwithdrawnhigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.