Bridgeport Fuel Cell I (394)

Bridgeport Fuel Cell I is a 5.6 MW gas interconnection project in Fairfield, Connecticut with a current status of operational. It is proposed to connect at UI 13.8 kV Ash Creek substation.

5.6 MWCapacity
OperationalStatus
SWCTMarket
GasTechnology

Project facts

Canonical nameBridgeport Fuel Cell I
Queue ID394
Statusoperational
Source statusC
MarketSWCT
TechnologyGas
Capacity5.6 MW
StateConnecticut
CountyFairfield
Point of interconnectionUI 13.8 kV Ash Creek substation
Requested (queue) date2012-07-25
Proposed in-service date
Operational date2013-12-22
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata