Brizo BESS (23INR0342)

Brizo BESS is a 144.2 MW other interconnection project in Victoria, Texas with a current status of operational. It is proposed to connect at 138 kV Loop 463 Substation (#5680).

144.2 MWCapacity
OperationalStatus
VictoriaMarket
OtherTechnology

Project facts

Canonical nameBrizo BESS
Queue ID23INR0342
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketVictoria
TechnologyOther
Capacity144.2 MW
StateTexas
CountyVictoria
Point of interconnection138 kV Loop 463 Substation (#5680)
Requested (queue) date2021-10-05
Proposed in-service date
Operational date2027-09-01
Withdrawn date
DeveloperBRP Brizo BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata