Brokaw - Clinton 345 kV line (J1676)

Brokaw - Clinton 345 kV line is a 300.0 MW wind interconnection project in McLean, Illinois with a current status of withdrawn. It is proposed to connect at Brokaw - Clinton 345 kV line.

300.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameBrokaw - Clinton 345 kV line
Queue IDJ1676
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity300.0 MW
StateIllinois
CountyMcLean
Point of interconnectionBrokaw - Clinton 345 kV line
Requested (queue) date2020-06-24
Proposed in-service date2023-04-20
Operational date2023-04-20
Withdrawn date2024-09-03
Developer
Utility / transmission ownerAMEREN ILLINOIS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.