BRP Kabru BESS (22INR0427)

BRP Kabru BESS is a 202.4 MW other interconnection project in Andrews, Texas with a current status of operational. It is proposed to connect at 1159 Andrew North - 11284 Blackbird 138kV.

202.4 MWCapacity
OperationalStatus
AndrewsMarket
OtherTechnology

Project facts

Canonical nameBRP Kabru BESS
Queue ID22INR0427
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketAndrews
TechnologyOther
Capacity202.4 MW
StateTexas
CountyAndrews
Point of interconnection1159 Andrew North - 11284 Blackbird 138kV
Requested (queue) date2020-10-07
Proposed in-service date
Operational date2028-12-01
Withdrawn date
DeveloperBRP Kabru BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata