Brushy Creek Solar B (21INR0436)
Brushy Creek Solar B is a 52.1 MW solar interconnection project with a current status of withdrawn. It is proposed to connect at 345 kV bus at San Angelo Red Creek (#6444)_x000D_ NOTE: This is for an increase in capacity for GINR 20INR0213 with the same POI.
Project facts
| Canonical name | Brushy Creek Solar B |
|---|---|
| Queue ID | 21INR0436 |
| Status | withdrawn |
| Source status | withdrawn |
| Market | ERCOT |
| Technology | Solar |
| Capacity | 52.1 MW |
| State | — |
| County | — |
| Point of interconnection | 345 kV bus at San Angelo Red Creek (#6444)_x000D_ NOTE: This is for an increase in capacity for GINR 20INR0213 with the same POI |
| Requested (queue) date | — |
| Proposed in-service date | 2021-12-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Brushy Creek Solar LLC |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.