Buckley Road 138kV (X2-058)

Buckley Road 138kV is a 149.5 MW wind interconnection project in Hancock, Ohio with a current status of withdrawn.

149.5 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameBuckley Road 138kV
Queue IDX2-058
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity149.5 MW
StateOhio
CountyHancock
Point of interconnection
Requested (queue) date2011-06-30
Proposed in-service date2012-11-15
Operational date
Withdrawn date2013-07-10
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.