Buckskin 69kV (AC2-055)

Buckskin 69kV is a 47.5 MW solar interconnection project in Highland, Ohio with a current status of withdrawn.

47.5 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameBuckskin 69kV
Queue IDAC2-055
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity47.5 MW
StateOhio
CountyHighland
Point of interconnection
Requested (queue) date2017-02-14
Proposed in-service date2019-07-01
Operational date
Withdrawn date2021-04-22
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.