Bunker Solar Energy Center (0802)

Bunker Solar Energy Center is a 125.0 MW battery interconnection project in Franklin, New York with a current status of withdrawn. It is proposed to connect at Willis - Lyon Mt 115kV.

125.0 MWCapacity
WithdrawnStatus
DMarket
BatteryTechnology

Project facts

Canonical nameBunker Solar Energy Center
Queue ID0802
Statuswithdrawn
Source status0
MarketD
TechnologyBattery
Capacity125.0 MW
StateNew York
CountyFranklin
Point of interconnectionWillis - Lyon Mt 115kV
Requested (queue) date2019-03-06
Proposed in-service date2020-03-31
Operational date
Withdrawn date
DeveloperEDF Renewables Development, Inc.
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.