Caldwell County Energy Center (30INR0031)

Caldwell County Energy Center is a 1,500.0 MW gas interconnection project in Caldwell, Texas with a current status of operational. It is proposed to connect at #7051 Misty Substation 345kV.

1,500.0 MWCapacity
OperationalStatus
CaldwellMarket
GasTechnology

Project facts

Canonical nameCaldwell County Energy Center
Queue ID30INR0031
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketCaldwell
TechnologyGas
Capacity1,500.0 MW
StateTexas
CountyCaldwell
Point of interconnection#7051 Misty Substation 345kV
Requested (queue) date2025-02-03
Proposed in-service date
Operational date2030-04-30
Withdrawn date
DeveloperCaldwell County Energy Center, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.