Cardington 138 kV II (AH2-217)

Cardington 138 kV II is a 100.0 MW battery interconnection project in Morrow, Ohio with a current status of withdrawn.

100.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameCardington 138 kV II
Queue IDAH2-217
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity100.0 MW
StateOhio
CountyMorrow
Point of interconnection—
Requested (queue) date2022-03-09
Proposed in-service date2026-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerATSI

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.