Cartanza 230 kV is a 120.0 MW solar interconnection project in Kent, Delaware with a current status of withdrawn.

120.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameCartanza 230 kV
Queue IDAG1-497 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity120.0 MW
StateDelaware
CountyKent
Point of interconnection—
Requested (queue) date2020-09-30
Proposed in-service date2023-06-30
Operational date—
Withdrawn date2025-01-22
Developer—
Utility / transmission ownerDPL

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata