Castro County 115kV (GEN-2025-GR6)

Castro County 115kV is a 300.0 MW wind interconnection project in Dimmit, Texas with a current status of active. It is proposed to connect at Castro County 115kV.

300.0 MWCapacity
ActiveStatus
TXMarket
WindTechnology

Project facts

Canonical nameCastro County 115kV
Queue IDGEN-2025-GR6
Statusactive
Source statusIA PENDING
MarketTX
TechnologyWind
Capacity300.0 MW
StateTexas
CountyDimmit
Point of interconnectionCastro County 115kV
Requested (queue) date2025-11-07
Proposed in-service date—
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.