Cathedral (2309)

Cathedral is a 361.1 MW solar+battery interconnection project in Nye, Nevada with a current status of withdrawn. It is proposed to connect at TROUT CANYON 500 kV.

361.1 MWCapacity
WithdrawnStatus
CAISOMarket
Solar+BatteryTechnology

Project facts

Canonical nameCathedral
Queue ID2309
Statuswithdrawn
Source statuswithdrawn
MarketCAISO
TechnologySolar+Battery
Capacity361.1 MW
StateNevada
CountyNye
Point of interconnectionTROUT CANYON 500 kV
Requested (queue) date2023-04-17
Proposed in-service date2031-12-02
Operational date
Withdrawn date2025-04-29
Developer
Utility / transmission ownerGLW

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.