Cedar Bayou 5 (68606_5)

Cedar Bayou 5 is a 721.0 MW gas interconnection project in Chambers, Texas with a current status of active.

721.0 MWCapacity
ActiveStatus
ERCOMarket
GasTechnology

Project facts

Canonical nameCedar Bayou 5
Queue ID68606_5
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketERCO
TechnologyGas
Capacity721.0 MW
StateTexas
CountyChambers
Point of interconnection
Requested (queue) date
Proposed in-service date2028-08-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerCedar Bayou 5 LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata