Cedro Hill Wind Repower (24INR0632)
Cedro Hill Wind Repower is a 9.9 MW other interconnection project in Webb, Texas with a current status of operational. It is proposed to connect at 80439 LA QUINTA 138kV.
9.9 MWCapacity
OperationalStatus
WebbMarket
OtherTechnology
Project facts
| Canonical name | Cedro Hill Wind Repower |
|---|---|
| Queue ID | 24INR0632 |
| Status | operational |
| Source status | SS Completed, FIS Completed, IA |
| Market | Webb |
| Technology | Other |
| Capacity | 9.9 MW |
| State | Texas |
| County | Webb |
| Point of interconnection | 80439 LA QUINTA 138kV |
| Requested (queue) date | 2023-09-28 |
| Proposed in-service date | — |
| Operational date | 2026-07-31 |
| Withdrawn date | — |
| Developer | Cedro Hill Wind, LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.