Central Hardin-Stephensburg 69 kV (AF2-309)

Central Hardin-Stephensburg 69 kV is a 70.0 MW solar interconnection project in Hardin, Kentucky with a current status of withdrawn.

70.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameCentral Hardin-Stephensburg 69 kV
Queue IDAF2-309
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity70.0 MW
StateKentucky
CountyHardin
Point of interconnection
Requested (queue) date2020-03-30
Proposed in-service date2023-09-01
Operational date
Withdrawn date2024-10-14
Developer
Utility / transmission ownerEKPC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.