Cernan BESS (27INR0392)

Cernan BESS is a 10.0 MW other interconnection project in Wharton, Texas with a current status of operational. It is proposed to connect at Hillje 345kV (#44200).

10.0 MWCapacity
OperationalStatus
WhartonMarket
OtherTechnology

Project facts

Canonical nameCernan BESS
Queue ID27INR0392
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketWharton
TechnologyOther
Capacity10.0 MW
StateTexas
CountyWharton
Point of interconnectionHillje 345kV (#44200)
Requested (queue) date2025-02-14
Proposed in-service date
Operational date2027-10-01
Withdrawn date
DeveloperCernan BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.