Chatfield-Howard 138kV (AC2-015)

Chatfield-Howard 138kV is a 117.0 MW solar interconnection project in Crawford, Ohio with a current status of operational.

117.0 MWCapacity
OperationalStatus
—Market
SolarTechnology

Project facts

Canonical nameChatfield-Howard 138kV
Queue IDAC2-015
Statusoperational
Source statusPartially in Service - Under Construction
Market—
TechnologySolar
Capacity117.0 MW
StateOhio
CountyCrawford
Point of interconnection—
Requested (queue) date2016-12-29
Proposed in-service date—
Operational date2025-12-16
Withdrawn date—
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata