Cherry Flats (0217)

Cherry Flats is a 90.0 MW wind interconnection project in Tioga, Pennsylvania with a current status of withdrawn. It is proposed to connect at Homer City-Watercure 345kV.

90.0 MWCapacity
WithdrawnStatus
CMarket
WindTechnology

Project facts

Canonical nameCherry Flats
Queue ID0217
Statuswithdrawn
Source status0
MarketC
TechnologyWind
Capacity90.0 MW
StatePennsylvania
CountyTioga
Point of interconnectionHomer City-Watercure 345kV
Requested (queue) date2006-06-06
Proposed in-service date2008-12-22
Operational date
Withdrawn date
DeveloperAES DE DEVCO NC LLC
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata