Cherry Valley Solar (1432)

Cherry Valley Solar is a 125.0 MW solar interconnection project in Montgomery, New York with a current status of withdrawn. It is proposed to connect at Edic - Princetown 345kV Line #351.

125.0 MWCapacity
WithdrawnStatus
FMarket
SolarTechnology

Project facts

Canonical nameCherry Valley Solar
Queue ID1432
Statuswithdrawn
Source status0
MarketF
TechnologySolar
Capacity125.0 MW
StateNew York
CountyMontgomery
Point of interconnectionEdic - Princetown 345kV Line #351
Requested (queue) date2022-09-07
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperCherry Valley Energy Center, L.L.C.
Utility / transmission ownerNYPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.