Chevron Green 115 kV Substation (ASGI-2023-001)

Chevron Green 115 kV Substation is a 20.0 MW solar interconnection project in Eddy, New Mexico with a current status of operational. It is proposed to connect at Chevron Green 115 kV Substation.

20.0 MWCapacity
OperationalStatus
NMMarket
SolarTechnology

Project facts

Canonical nameChevron Green 115 kV Substation
Queue IDASGI-2023-001
Statusoperational
Source statusNone
MarketNM
TechnologySolar
Capacity20.0 MW
StateNew Mexico
CountyEddy
Point of interconnectionChevron Green 115 kV Substation
Requested (queue) date2023-10-02
Proposed in-service date
Operational date2022-12-09
Withdrawn date
Developer
Utility / transmission ownerSPS

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata