Cielo Vista Power II (28INR0497)
Cielo Vista Power II is a 350.4 MW gas interconnection project in Duval, Texas with a current status of active. It is proposed to connect at TAP 345 kV BUS # 5901 MIGUEL5 - BUS #80280 CRUCE SM 7A Ckt-1.
350.4 MWCapacity
ActiveStatus
DuvalMarket
GasTechnology
Project facts
| Canonical name | Cielo Vista Power II |
|---|---|
| Queue ID | 28INR0497 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Duval |
| Technology | Gas |
| Capacity | 350.4 MW |
| State | Texas |
| County | Duval |
| Point of interconnection | TAP 345 kV BUS # 5901 MIGUEL5 - BUS #80280 CRUCE SM 7A Ckt-1 |
| Requested (queue) date | 2026-07-06 |
| Proposed in-service date | 2028-12-29 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Cielo Wind Power |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata