Circleville-Biers Run 138 kV (AH1-669 - formerly AG1-326 - moved to TC2)

Circleville-Biers Run 138 kV is a 50.0 MW solar interconnection project in Ross, Ohio with a current status of withdrawn.

50.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameCircleville-Biers Run 138 kV
Queue IDAH1-669 - formerly AG1-326 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity50.0 MW
StateOhio
CountyRoss
Point of interconnection
Requested (queue) date2020-09-30
Proposed in-service date2029-12-31
Operational date
Withdrawn date2025-12-02
Developer
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata