CO Queue Project 2017-G5 — Solar in Logan County, Colorado

CO Queue Project 2017-G5 — Solar in Logan County, Colorado is a 50.0 MW solar interconnection project in Logan County, Colorado with a current status of withdrawn. It is proposed to connect at Sidney - Sterling 115-kV.

50.0 MWCapacity
WithdrawnStatus
COMarket
SolarTechnology

Project facts

Canonical nameCO Queue Project 2017-G5 — Solar in Logan County, Colorado
Queue ID2017-G5
Statuswithdrawn
Source statusWithdrawn
MarketCO
TechnologySolar
Capacity50.0 MW
StateColorado
CountyLogan County
Point of interconnectionSidney - Sterling 115-kV
Requested (queue) date2017-07-21
Proposed in-service date2019-07-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerWestern Area Power Administration - Rocky Mountain Region

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata