CO Queue Project 3RSC-2023-03 — Wind in Kiowa County, Colorado

CO Queue Project 3RSC-2023-03 — Wind in Kiowa County, Colorado is a 200.0 MW wind interconnection project in Kiowa County, Colorado with a current status of withdrawn. It is proposed to connect at May Valley 345 kV.

200.0 MWCapacity
WithdrawnStatus
COMarket
WindTechnology

Project facts

Canonical nameCO Queue Project 3RSC-2023-03 — Wind in Kiowa County, Colorado
Queue ID3RSC-2023-03
Statuswithdrawn
Source statusWithdrawn 4/22/2026
MarketCO
TechnologyWind
Capacity200.0 MW
StateColorado
CountyKiowa County
Point of interconnectionMay Valley 345 kV
Requested (queue) date2023-05-19
Proposed in-service date2025-12-31
Operational date
Withdrawn date2026-04-22
Developer
Utility / transmission ownerPublic Service Company Of Colorado

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: psco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.