CO Queue Project 5RSC-2024-17 — Wind in Kit Carson County, Colorado
CO Queue Project 5RSC-2024-17 — Wind in Kit Carson County, Colorado is a 603.0 MW wind interconnection project in Kit Carson County, Colorado with a current status of operational. It is proposed to connect at Goose Creek 345 kV Substation.
603.0 MWCapacity
OperationalStatus
COMarket
WindTechnology
Project facts
| Canonical name | CO Queue Project 5RSC-2024-17 — Wind in Kit Carson County, Colorado |
|---|---|
| Queue ID | 5RSC-2024-17 |
| Status | operational |
| Source status | Cluster Study Completed |
| Market | CO |
| Technology | Wind |
| Capacity | 603.0 MW |
| State | Colorado |
| County | Kit Carson County |
| Point of interconnection | Goose Creek 345 kV Substation |
| Requested (queue) date | 2024-01-24 |
| Proposed in-service date | — |
| Operational date | 2026-05-07 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Public Service Company Of Colorado |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-11-02 | phase | — | Cluster Study Report posted 10/5/2026 | low |
| 2026-11-02 | operational_date | — | 2026-05-07 | medium |
| 2026-11-02 | proposed_online_date | 2026-05-07 | — | medium |
| 2026-11-02 | status | active | operational | high |
| 2026-08-02 | new_project | — | active | high |
Explore related data
Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26
Provenance: psco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.