CO Queue Project 7RSC-2026-03 — Wind in Kit Carson County, Colorado
CO Queue Project 7RSC-2026-03 — Wind in Kit Carson County, Colorado is a 600.0 MW wind interconnection project in Kit Carson County, Colorado with a current status of active. It is proposed to connect at Goose Creek - Canal Crosssing 345 kV Line.
600.0 MWCapacity
ActiveStatus
COMarket
WindTechnology
Project facts
| Canonical name | CO Queue Project 7RSC-2026-03 — Wind in Kit Carson County, Colorado |
|---|---|
| Queue ID | 7RSC-2026-03 |
| Status | active |
| Source status | Study to be started after completion of 6RSC Cluster |
| Market | CO |
| Technology | Wind |
| Capacity | 600.0 MW |
| State | Colorado |
| County | Kit Carson County |
| Point of interconnection | Goose Creek - Canal Crosssing 345 kV Line |
| Requested (queue) date | 2026-04-01 |
| Proposed in-service date | 2029-02-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Public Service Company Of Colorado |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-02 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: psco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata