CO Queue Project BHCT-G53 — Solar in Pueblo, Colorado

CO Queue Project BHCT-G53 — Solar in Pueblo, Colorado is a 150.0 MW solar interconnection project in Pueblo, Colorado with a current status of withdrawn. It is proposed to connect at Baculite Mesa 115 kV Substation.

150.0 MWCapacity
WithdrawnStatus
COMarket
SolarTechnology

Project facts

Canonical nameCO Queue Project BHCT-G53 — Solar in Pueblo, Colorado
Queue IDBHCT-G53
Statuswithdrawn
Source statusWithdrawn
MarketCO
TechnologySolar
Capacity150.0 MW
StateColorado
CountyPueblo
Point of interconnectionBaculite Mesa 115 kV Substation
Requested (queue) date2024-06-14
Proposed in-service date2027-10-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerBlack Hills Colorado Electric

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: blackhills-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.