CO Queue Project GI-2025-08 — Solar+Battery in El Paso County, Colorado

CO Queue Project GI-2025-08 — Solar+Battery in El Paso County, Colorado is a 400.0 MW solar+battery interconnection project in El Paso County, Colorado with a current status of withdrawn. It is proposed to connect at Sandstone-Harvest Mile 345 kV line.

400.0 MWCapacity
WithdrawnStatus
COMarket
Solar+BatteryTechnology

Project facts

Canonical nameCO Queue Project GI-2025-08 — Solar+Battery in El Paso County, Colorado
Queue IDGI-2025-08
Statuswithdrawn
Source statusWithdrawn 03/09/2026
MarketCO
TechnologySolar+Battery
Capacity400.0 MW
StateColorado
CountyEl Paso County
Point of interconnectionSandstone-Harvest Mile 345 kV line
Requested (queue) date2025-04-25
Proposed in-service date2029-09-19
Operational date
Withdrawn date2026-03-09
Developer
Utility / transmission ownerPublic Service Company Of Colorado

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: psco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.