CO Queue Project GI-TC-2024-32 — Solar in Moffat County, Colorado

CO Queue Project GI-TC-2024-32 — Solar in Moffat County, Colorado is a 66.5 MW solar interconnection project in Moffat County, Colorado with a current status of withdrawn. It is proposed to connect at Craig 230kV Substation.

66.5 MWCapacity
WithdrawnStatus
COMarket
SolarTechnology

Project facts

Canonical nameCO Queue Project GI-TC-2024-32 — Solar in Moffat County, Colorado
Queue IDGI-TC-2024-32
Statuswithdrawn
Source statusWithdrawn
MarketCO
TechnologySolar
Capacity66.5 MW
StateColorado
CountyMoffat County
Point of interconnectionCraig 230kV Substation
Requested (queue) date2024-05-23
Proposed in-service date2027-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerTri-State Generation and Transmission Association

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: tristate-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.