Coldwater-Rossburg 69kV (T48)

Coldwater-Rossburg 69kV is a 40.0 MW wind interconnection project in Mercer, Ohio with a current status of withdrawn.

40.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameColdwater-Rossburg 69kV
Queue IDT48
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity40.0 MW
StateOhio
CountyMercer
Point of interconnection
Requested (queue) date2007-09-21
Proposed in-service date2013-11-30
Operational date
Withdrawn date2012-05-09
Developer
Utility / transmission ownerDayton

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata