Colorado Bend Energy Center 2 (06INR0035a)

Colorado Bend Energy Center 2 is a 275.0 MW gas interconnection project with a current status of operational. It is proposed to connect at CBEC_GT3 13.800.

275.0 MWCapacity
OperationalStatus
ERCOTMarket
GasTechnology

Project facts

Canonical nameColorado Bend Energy Center 2
Queue ID06INR0035a
Statusoperational
Source statusoperational
MarketERCOT
TechnologyGas
Capacity275.0 MW
State
County
Point of interconnectionCBEC_GT3 13.800
Requested (queue) date2005-05-11
Proposed in-service date2007-04-01
Operational date
Withdrawn date
DeveloperNavasota Wharton Energy Partners
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata