Columbia County 1 (0644)
Columbia County 1 is a 60.0 MW solar interconnection project in Columbia, New York with a current status of active. It is proposed to connect at Craryville 115kV.
60.0 MWCapacity
ActiveStatus
FMarket
SolarTechnology
Project facts
| Canonical name | Columbia County 1 |
|---|---|
| Queue ID | 0644 |
| Status | active |
| Source status | 11 |
| Market | F |
| Technology | Solar |
| Capacity | 60.0 MW |
| State | New York |
| County | Columbia |
| Point of interconnection | Craryville 115kV |
| Requested (queue) date | 2017-07-26 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | Hecate Energy |
| Utility / transmission owner | NYSEG |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata