Combined Reciprocating, Solar and Battery modification (780)

Combined Reciprocating, Solar and Battery modification is a 7.8 MW solar+battery interconnection project in Middlesex, Massachusetts with a current status of withdrawn. It is proposed to connect at GRID Hendersonville 593 substation (593W1 and 593W4).

7.8 MWCapacity
WithdrawnStatus
BOSTMarket
Solar+BatteryTechnology

Project facts

Canonical nameCombined Reciprocating, Solar and Battery modification
Queue ID780
Statuswithdrawn
Source statusW
MarketBOST
TechnologySolar+Battery
Capacity7.8 MW
StateMassachusetts
CountyMiddlesex
Point of interconnectionGRID Hendersonville 593 substation (593W1 and 593W4)
Requested (queue) date2018-09-11
Proposed in-service date2022-05-31
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata