COOLEY LANDING BESS (1101)
COOLEY LANDING BESS is a 20.0 MW battery interconnection project in San Mateo, California with a current status of withdrawn. It is proposed to connect at Cooley Landing 60kV Substation.
20.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology
Project facts
| Canonical name | COOLEY LANDING BESS |
|---|---|
| Queue ID | 1101 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | — |
| Technology | Battery |
| Capacity | 20.0 MW |
| State | California |
| County | San Mateo |
| Point of interconnection | Cooley Landing 60kV Substation |
| Requested (queue) date | 2015-04-30 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2016-04-15 |
| Developer | — |
| Utility / transmission owner | PGAE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.