Cornerstone Solar (AH1-545)

Cornerstone Solar is a 200.0 MW solar interconnection project in Washington, Pennsylvania with a current status of active. It is proposed to connect at Wylie Ridge-Tidd 345kV.

200.0 MWCapacity
ActiveStatus
PJMMarket
SolarTechnology

Project facts

Canonical nameCornerstone Solar
Queue IDAH1-545
Statusactive
Source statusactive
MarketPJM
TechnologySolar
Capacity200.0 MW
StatePennsylvania
CountyWashington
Point of interconnectionWylie Ridge-Tidd 345kV
Requested (queue) date2025-02-25
Proposed in-service date2025-03-01
Operational date
Withdrawn date
DeveloperCornerstone Solar, LLC
Utility / transmission ownerAPS

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata