Crape Myrtle Solar (28INR0531)
Crape Myrtle Solar is a 140.7 MW solar interconnection project in Ellis, Texas with a current status of active. It is proposed to connect at Tap 345 kV 2255 OLDCNTRY_5 - 3376 NOTUS_5.
140.7 MWCapacity
ActiveStatus
EllisMarket
SolarTechnology
Project facts
| Canonical name | Crape Myrtle Solar |
|---|---|
| Queue ID | 28INR0531 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Ellis |
| Technology | Solar |
| Capacity | 140.7 MW |
| State | Texas |
| County | Ellis |
| Point of interconnection | Tap 345 kV 2255 OLDCNTRY_5 - 3376 NOTUS_5 |
| Requested (queue) date | — |
| Proposed in-service date | 2028-06-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Crape Myrtle Solar LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata