Crossroads - Hobbs 345 kV Line (GEN-2022-159)

Crossroads - Hobbs 345 kV Line is a 280.0 MW wind interconnection project in Chaves And Lea, New Mexico with a current status of withdrawn. It is proposed to connect at Crossroads - Hobbs 345 kV Line.

280.0 MWCapacity
WithdrawnStatus
NMMarket
WindTechnology

Project facts

Canonical nameCrossroads - Hobbs 345 kV Line
Queue IDGEN-2022-159
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologyWind
Capacity280.0 MW
StateNew Mexico
CountyChaves And Lea
Point of interconnectionCrossroads - Hobbs 345 kV Line
Requested (queue) date2023-02-24
Proposed in-service date2027-12-01
Operational date
Withdrawn date2025-03-06
Developer
Utility / transmission ownerNEET

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.