Crossroads Wind (26INR0021)

Crossroads Wind is a 276.8 MW other interconnection project in Victoria, Texas with a current status of operational. It is proposed to connect at 80090 Dokmai 138 KV.

276.8 MWCapacity
OperationalStatus
VictoriaMarket
OtherTechnology

Project facts

Canonical nameCrossroads Wind
Queue ID26INR0021
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketVictoria
TechnologyOther
Capacity276.8 MW
StateTexas
CountyVictoria
Point of interconnection80090 Dokmai 138 KV
Requested (queue) date2022-09-27
Proposed in-service date—
Operational date2027-09-30
Withdrawn date—
DeveloperHyFuels Green Lake Wind LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31developer—HyFuels Green Lake Wind LLClow
2026-08-31poi_name—80090 Dokmai 138 KVlow
2026-08-31phase—SS Completed, FIS Completed, IAlow
2026-08-31ia_signed_date—2024-07-24medium
2026-08-31operational_date—2027-09-30medium
2026-08-31statussuspendedoperationalhigh
2026-07-31new_project—suspendedhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata