CVH POWER II (808)
CVH POWER II is a 700.0 MW solar interconnection project in Maricopa, Arizona with a current status of withdrawn. It is proposed to connect at Harquahala Substation 500kV .
700.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology
Project facts
| Canonical name | CVH POWER II |
|---|---|
| Queue ID | 808 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | — |
| Technology | Solar |
| Capacity | 700.0 MW |
| State | Arizona |
| County | Maricopa |
| Point of interconnection | Harquahala Substation 500kV |
| Requested (queue) date | 2011-03-31 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2011-08-05 |
| Developer | — |
| Utility / transmission owner | SCE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.