Daisy Solar (28INR0535)

Daisy Solar is a 200.9 MW solar interconnection project in Foard, Texas with a current status of active. It is proposed to connect at Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B.

200.9 MWCapacity
ActiveStatus
FoardMarket
SolarTechnology

Project facts

Canonical nameDaisy Solar
Queue ID28INR0535
Statusactive
Source statusSS Started, FIS Started, No IA
MarketFoard
TechnologySolar
Capacity200.9 MW
StateTexas
CountyFoard
Point of interconnectionTap 345kV 6101 RILEY7A - 60505 EDITHCLA7B
Requested (queue) date2026-07-06
Proposed in-service date2029-06-30
Operational date—
Withdrawn date—
DeveloperDaisy Solar LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30proposed_online_date2028-06-152029-06-30medium
2026-08-31new_project—activehigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.