Damia Solar is a 306.0 MW solar interconnection project in Eastland, Texas with a current status of operational. It is proposed to connect at Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8 .

306.0 MWCapacity
OperationalStatus
EastlandMarket
SolarTechnology

Project facts

Canonical nameDamia Solar
Queue ID26INR0603
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEastland
TechnologySolar
Capacity306.0 MW
StateTexas
CountyEastland
Point of interconnectionTap 138kV 6317 Cisco - 3545 MTNBRANCH_8
Requested (queue) date2025-04-01
Proposed in-service date
Operational date2028-07-01
Withdrawn date
DeveloperDamia Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.