Dart Energy Storage A1 (28INR0293)

Dart Energy Storage A1 is a 50.0 MW other interconnection project in Taylor, Texas with a current status of operational. It is proposed to connect at TAP138KV #6290 ABILENE MAPLE STREET - #6275 ABILENE EAST.

50.0 MWCapacity
OperationalStatus
TaylorMarket
OtherTechnology

Project facts

Canonical nameDart Energy Storage A1
Queue ID28INR0293
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketTaylor
TechnologyOther
Capacity50.0 MW
StateTexas
CountyTaylor
Point of interconnectionTAP138KV #6290 ABILENE MAPLE STREET - #6275 ABILENE EAST
Requested (queue) date2025-02-25
Proposed in-service date
Operational date2028-11-30
Withdrawn date
DeveloperDart Energy Storage LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.