Desert Vine Solar (22INR0307)

Desert Vine Solar is a 121.3 MW solar interconnection project with a current status of withdrawn. It is proposed to connect at Tap 138kV 8957 Lopeno - 8299 Zapata _x000D_ Will be TSP’s Snapdragon Station.

121.3 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameDesert Vine Solar
Queue ID22INR0307
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity121.3 MW
State
County
Point of interconnectionTap 138kV 8957 Lopeno - 8299 Zapata _x000D_ Will be TSP’s Snapdragon Station
Requested (queue) date2020-05-01
Proposed in-service date2026-12-30
Operational date
Withdrawn date
DeveloperDesert Solar
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.