DG AMP Solar Jackson Center (61438_AMPJC)

DG AMP Solar Jackson Center is a 1.6 MW solar interconnection project in Shelby, Ohio with a current status of operational.

1.6 MWCapacity
OperationalStatus
PJMMarket
SolarTechnology

Project facts

Canonical nameDG AMP Solar Jackson Center
Queue ID61438_AMPJC
Statusoperational
Source status(OP) Operating
MarketPJM
TechnologySolar
Capacity1.6 MW
StateOhio
CountyShelby
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2018-02-01
Withdrawn date—
Developer—
Utility / transmission ownerDG AMP Solar, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.