Donegal-Iron City 138kV (Q25)

Donegal-Iron City 138kV is a 80.0 MW wind interconnection project in Fayette, Pennsylvania with a current status of withdrawn.

80.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameDonegal-Iron City 138kV
Queue IDQ25
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity80.0 MW
StatePennsylvania
CountyFayette
Point of interconnection
Requested (queue) date2006-03-24
Proposed in-service date2014-03-01
Operational date
Withdrawn date2012-06-04
Developer
Utility / transmission ownerAPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.