Dumont 345 kV (AG2-230 - moved to TC2)

Dumont 345 kV is a 150.0 MW solar interconnection project in St. Joseph, Indiana with a current status of active.

150.0 MWCapacity
ActiveStatus
—Market
SolarTechnology

Project facts

Canonical nameDumont 345 kV
Queue IDAG2-230 - moved to TC2
Statusactive
Source statusActive
Market—
TechnologySolar
Capacity150.0 MW
StateIndiana
CountySt. Joseph
Point of interconnection—
Requested (queue) date2021-03-12
Proposed in-service date2030-10-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-01proposed_online_date—2030-10-31medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.