Dumont-Greentown 765 kV (AG2-165 - moved to TC2)

Dumont-Greentown 765 kV is a 200.0 MW solar interconnection project in Marshall, Indiana with a current status of withdrawn.

200.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameDumont-Greentown 765 kV
Queue IDAG2-165 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity200.0 MW
StateIndiana
CountyMarshall
Point of interconnection
Requested (queue) date2021-02-25
Proposed in-service date2028-12-31
Operational date
Withdrawn date2025-11-27
Developer
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata